What are the critical path activities what is the projects


Problem 1

The following data were obtained from an in-house MIS project-

Activity Duration Predecessors 

A        3 Days   ---          

B        6 Days   ---          

C        3 Days   B            

D        2 Days   A            

E        3 Days   C,D          

F        2 Days   A            

G        4 Days   F            

H        7 Days   B

I        2 Days   C,D

J        4 Days   H,I

K        8 Days   H,I

L        5 Days   E,G,Ja) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity E? Show your calculations.

f) What is the slack or float for Activity J? Show your calculations.

Problem 2.

A project to remodel an office area has the following activities.

Activity

Duration

Predecessors

A

3 months

---

B

2 months

---

C

3 months

---

D

4 months

A, B

E

3 months

A

F

2 months

B, C

G

2 months

F

H

1 month

G

I

4 months

D, E, F

J

5 months

H

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity B? Show your calculations.

d) What is the slack or float for Activity D? Show your calculations.

e) What is the slack or float for Activity F? Show your calculations.

f) What is the slack or float for Activity I? Show your calculations.

Problem 3

Information from a room addition project:

 

 

Duration

Predecessors

 

A

2 wks

 

 

B

3 wks

 

 

C

5 wks

 

 

D

7 wks

A

 

E

3 wks

B

 

F

2 wks

C

 

G

4 wks

F

 

H

1 wk

A

 

I

8 wks

D, E, G

 

J

5 wks

F

 

K

2 wks

D, E, G, H

 

 

 

 

 

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity A? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity H? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations.

Problem 4

InformAtion from a site renovation project:

Task     Duration            Predecessors

A          2 wks               _

B          5 WKS             A

C          3 WKS             B

D          15 WKS           B

E          8 WKS             C

F          10 WKS           C

G         2 WKS             D

H          6 WKS             E, F, G

I           5 WKS             H

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity I? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What are the critical path activities what is the projects
Reference No:- TGS0984949

Expected delivery within 24 Hours