What are the cpi and spi


A construction project at day 70 exhibits an actual cost of $78,000, and a scheduled cost of $84,000. The foreman estimates a value completed of $81,000.

Required:

Question: What are the spending (cost) and schedule variances?

Question: What are the CPI and SPI? Is the project ahead of schedule or behind? Is it over budget or under budget?

Note: Please show how you came up with the solution.

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: What are the cpi and spi
Reference No:- TGS0878622

Expected delivery within 24 Hours