What are the cost and schedule variances what are the three


At week 24 of a project to shoot a television commercial, what should the expenditures be? If the earned value is right on schedule but the actual expenses are $9,000, what are the cost and schedule variances? What are the three indexes, the ETC, and the EAC? Use the proportionality rule.