SOLVING FOR UNKNOWNS

Misterio Company uses a standard costing system. During the past quarter, the following variances were computed:

Variable overhead efficiency variance

$ 24,000 U

Direct labor efficiency variance

120,000 U

Direct labor rate variance

10,400 U

Misterio applies variable overhead using a standard rate of $2 per direct labor hour allowed. Two direc labor hours are allowed per unit produced. (Only one type of product is manufactured.) During th quarter, Misterio used 30 percent more direct labor hours than should have been used

Required:

1. What were the actual direct labor hours worked? The total hours allowed?

2. What is the standard hourly rate for direct labor? The actual hourly rate?

3. How many actual units were produced?

Solution Preview :