What and when is the second milestone - what are the last


1. Your PM experience:

a. I have prior experience in project management. Yes/No No

b. I have used PM software. Yes/No No

2. The Triple Constraint in PM refers to meeting simultaneously the requirements of time, cost and Scope.

3. After installing MS-Project (MSP) 2010 or 2013 (preferred because newer) (trial version found at microsoft.com, full version available via the UMUC-Microsoft Alliance "Dreamspark"), download and open the file, "LRE1_MPP_MS_Project_Renovation_Example.mpp", attached below and also at mpp file, to answer the following questions: (Example chart uploaded)

a. When is this project expected to end? 6/4/10

b. What and when is the second milestone? Receive Final Plan 4/28/10

c. What are the last two tasks on the project critical path? Furniture Delivery and Unpack

4. Using the following table of tasks,

a. Build using MSP an mpp file including a work breakdown structure and a Gantt chart showing the project critical path.

b. What does the critical path become if Task C takes three time units?

Task

Predecessor(s)

Time units required

A

None

1

B

A

2

C

A

1

D

B and C

1

Solution Preview :

Prepared by a verified Expert
Dissertation: What and when is the second milestone - what are the last
Reference No:- TGS02175089

Now Priced at $10 (50% Discount)

Recommended (97%)

Rated (4.9/5)