Webster Manufacturing Inc. is implementing a Just-in-Time (JIT) system and wants to know how many Kanbans to use for the initial setup of its JIT system. The daily demand is 400 units and each Kanban (i.e., container) holds 15 units. The combined processing and waiting time per container is 0.7 days. If the initial alpha value for safety stock is 0.6, what is the maximum authorized inventory?