We assume what the project has experienced to date will be


Your budget completion for your project is $790,000. You earned $430,000. After checking your invoice and receipts, you found one of the pieces of equipment you ordered was $450.000. We assume what the project has experienced to date will be expected to continue in the future. What is your estimate at completion.

A 790,000

B 805,000

C 810,000

D 831,000