We are evaluating a project that costs 1675000 has a


We are evaluating a project that costs $1,675,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 91,000 units per year. Price per unit is $35.95, variable cost per unit is $21.40, and fixed costs are $775,000 per year. The tax rate is 35 percent, and we require a return of 11 percent on this project. Required: Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent. Calculate the best-case and worst-case NPV figures. (Do not round intermediate calculations. Negative amounts should be indicated by a minus sign. Round your answers to 2 decimal places (e.g., 32.16).) NPV Best-case $ Worst-case $

Request for Solution File

Ask an Expert for Answer!!
Financial Management: We are evaluating a project that costs 1675000 has a
Reference No:- TGS02137739

Expected delivery within 24 Hours