We are evaluating a project that costs 1120000 has a


Calculate the best-case and worst-case NPV figures. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))

We are evaluating a project that costs $1,120,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 64,000 units per year. Price per unit is $50, variable cost per unit is $25, and fixed costs are $620,000 per year. The tax rate is 35 percent, and we require a 12 percent return on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent.

Solution Preview :

Prepared by a verified Expert
Business Economics: We are evaluating a project that costs 1120000 has a