We are evaluating a project that costs 1080000 has a


We are evaluating a project that costs $1,080,000, has a ten-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 52,000 units per year. Price per unit is $50, variable cost per unit is $30, and fixed costs are $730,000 per year. The tax rate is 35 percent, and we require a return of 15 percent on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±10 percent. Calculate the best-case and worst-case NPV figures. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your final answers to 2 decimal places (e.g., 32.16).)

NPV Best-case $ Worst-case $

Request for Solution File

Ask an Expert for Answer!!
Financial Management: We are evaluating a project that costs 1080000 has a