Usingnbspa 5nbsp05 and the following data compute


Using a 5 0.5 and the following data, compute exponential smoothing forecasts for periods 2 through 8.

Period:

1

2

3

4

5

6

7

Forecast:

10

 

 

 

 

 

 

Actual demand:

12

15

11

13

11

11

10

Text Book: Managing Operation Across the Supply Chain 2nd Edition.