Using visual inspection standards and traditional methods


Using visual inspection standards and traditional methods, some 100 defects are located in a large batch of product. What is the best estimate of the total number of defects in the product before inspection?

a. 95-98

b. 108-111

c. 117-120

d. 125-128

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Using visual inspection standards and traditional methods
Reference No:- TGS01268500

Expected delivery within 24 Hours