Using the table below enter the information into ms project


Resource Evaluation

Produce and complete a a Gantt Chart using MS Project software.

  • Using the Table below enter the information into MS Project software. Assume that each resource has been assigned to the project activity on a full-time (8 hours /day or 40 hours per week) basis
Activity Duration Predecessors Resource Assigned
A. User Survey 4 None Gail Wilkins
B. Coding 12 A Tom Hodges
C. Debugging 5 B Wilson Pitts
D. Design Interface 6 A,C Sue Ryan
E. Develop Training 5 D Reed Taylor

Include a title page and adhere to the Publication Manual of the American Psycholgical Association (APA), (6th ed., 2nd printing) when writing and submitting assignments and papers.

Solution Preview :

Prepared by a verified Expert
Other Engineering: Using the table below enter the information into ms project
Reference No:- TGS01417146

Now Priced at $40 (50% Discount)

Recommended (94%)

Rated (4.6/5)