Using the pert program evaluation review technique


Chapter 8 Homework Assignment

Questions

1. Draw an Activity-on-Arrow Diagram for the following:

Activity Name

Predecessor(s)

A

None

B

None

C

A

D

A,B

E

D

F

E

2. Draw an Activity-on-Node Diagram for the following:

Activity Name

Predecessor(s)

A

None

B

None

C

A

D

A,B

E

D

F

E

3. Should the critical path activities be managed differently from non-critical path activities for a project?  Explain your response.

4. Using the PERT (Program Evaluation Review Technique) estimating method, calculate the expected time (TE) for each of the following activities.  Round to the nearest whole number using standard rounding.

Activity

Optimistic (days)

Pessimistic (days)

Most Likely (days)

Activity A

2

12

4

Activity B

5

25

20

Activity C

10

50

18

Activity D

3

10

7

5. Draw an Activity-on-Node Diagram, identify project duration, slack for each activity,  and project critical path for the following:

Activity Name

Predecessor(s)

Duration (Weeks)

A

None

5

B

None

10

C

None

5

D

A,B

5

E

C

10

F

C,D

15

G

E,F

5

6. Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity, project duration, and project critical path for the following.  Don't forget that you have to compute the duration using the PERT formula (a+4m+b/6).  Round to the nearest whole number using standard rounding.

Activity Name

Predecessor(s)

a

m

b

A

None

5

20

40

B

None

10

25

50

C

None

5

10

50

D

A,B

5

10

30

E

C

10

20

40

F

C,D

10

20

60

G

E,F

5

20

40

Solution Preview :

Prepared by a verified Expert
Operation Management: Using the pert program evaluation review technique
Reference No:- TGS02839688

Now Priced at $20 (50% Discount)

Recommended (96%)

Rated (4.8/5)