Using the percentage-of-completion method compute the


Question: On March 1, 2014, Pechstein Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,736,000. The building was completed by October 31, 2016. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2014, 2015, and 2016 are given below.



2014
2015
2016
Contract costs incurred during the year
$2,995,200
$2,319,200
$2,277,600
Estimated costs to complete the contract at 12/31
3,660,800
2,277,600
0
Billings to Fabrik during the year
3,328,000
3,640,000
1,768,000

Using the percentage-of-completion method, compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Ignore income taxes.) (Enter loss amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)



2014
2015
2016
Profit/ (Loss)
$


$


$


Using the completed-contract method, compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2014, 2015, and 2016. (Ignore incomes taxes.) (Enter loss amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)



2014
2015
2016
Profit/ (Loss)
$


$


$

Solution Preview :

Prepared by a verified Expert
Accounting Basics: Using the percentage-of-completion method compute the
Reference No:- TGS02555693

Now Priced at $20 (50% Discount)

Recommended (91%)

Rated (4.3/5)