using the information given in the following


Using the information given in the following table: (A) Identify the critical path. (B) Determine expected project duration. Activities Precedes Duration Start a,b,c - a d 5 d f 6 f g 2 b e 5 e f 9 c h 4 h g,i 6 g end 3 l end 1