Using the forward passbackward pass technique derive the


Activity schedule and modified bar chart.

Using the forward pass/backward pass technique derive the activity schedule and modified bar chart for the arrow diagram shown. What is the critical part? Project duration?

2216_Fig 7.jpg

Request for Solution File

Ask an Expert for Answer!!
Management Information Sys: Using the forward passbackward pass technique derive the
Reference No:- TGS01699210