Using the following draw project costs over time cash flow


Using the following draw project costs over time, cash flow, earned value, and break-even analysis. And also write a 75 word paper on how project costs will be monitored and managed. Also complete the Earned value, Actual cost and budget box. Or you can change the whole numbers around.

Budget

Task/Date

1-Jul-14

14-Jul-14

17-Aug-14

13-Sep-14

20-Sep-14

$4,000

Initiation

50%

100%

100%

100%

100%

$4,000

Planning

0%

50%

100%

100%

100%

$8,000

Execution

0%

50%

100%

100%

100%

$4,000

Control

50%

100%

100%

100%

100%

$7,000

Closeout

0%

0%

25%

50%

100%

 

Earned Value

 

 

 

 

 

 

Actual Cost

 

 

 

 

 

 

Budget

 

 

 

 

 