Using the cumulative data provided from the integrated


Using the cumulative data provided from the Integrated Program Management Report, what is the cost performance index (CPI) for the Armament Work Breakdown Structure (WBS) element?

(IMAGE DESCRIPTION: WBS number 1.1.5, Armament, has a BCWS of 3049, a BCWP of 2807, an ACWP of 3262, a BAC of 3818, and an EAC of 4510.)