Using the cumulative data from the ipmr below for wbs 115


Using the cumulative data from the IPMR below for WBS 1.1.5, calculate a formula-based estimate at completion (EAC) using the performance factor of cost performance index times schedule performance index, or CPI x SPI.

WBS number 1.1.5, Armament, has a BCWS of 3049, a BCWP of 2807, an ACWP of 3262, a BAC of 3818, and an EAC of 4510

Please select answer from options below.

4538.2

4436.9

1275.4

4358.8

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Using the cumulative data from the ipmr below for wbs 115
Reference No:- TGS01183927

Expected delivery within 24 Hours