Using the critical ratio priority rule for one


A manufacturing facility has five jobs to be scheduled into production. The following table gives the processing times plus the necessary wait times and other necessary delays for each of the jobs. Assume that today is April 3 and the jobs are due on the dates shown:

Job Processing Time Delay Time Total Time Due Date

1 2 12 14 27
2 5 8 13 18
3 9 15 24 25
4 7 9 16 26
5 4 22 28 24

Determine two schedules, starting the order in which the jobs are to be done. Use the critical ratio priority rule for one. You may use any other run for the second schedule as long as you state what it is. (I was using EDD-Earliest due date firs. But you can use the same.