Using the activity table below construct a cpmpert network


Question: Using the activity table below, construct a CPM/PERT network noting the activity numbers and durations. Identify the critical path through the network, determine the project completion time, and determine the earliest and latest end dates for each node. Create your network in Microsoft Word and submit it to your instructor.

Activity

Predecessor

Time (months)

1

-

10

2

-

1

3

-

6

4

2

3

5

1,3,4

5

6

3

8

7

5,6

2

Request for Solution File

Ask an Expert for Answer!!
Management Theories: Using the activity table below construct a cpmpert network
Reference No:- TGS02694844

Expected delivery within 24 Hours