Using the activity table below construct a cpmpert network


Question: Using the activity table below, construct a CPM/PERT network noting the activity numbers and durations. Identify the critical path through the network, determine the project completion time, and determine the earliest and latest end dates for each node. Create your network in Microsoft Word and submit it to your instructor. Please do not draw.

Activity

Predecessor

Time (months)

1

-

10

2

-

1

3

-

6

4

2

3

5

1,3,4

5

6

3

8

7

5,6

2