Using the 50-50 rule earned value computation what is


1) Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100

 

Task B

4,000

Yes

Yes

4,500

 

Task C

2,500

Yes

Yes

2,250

 

Task D

4,000

Yes

No

3,500

 

Task E

3,500

Yes

Yes

4,000

 

Task F

2,500

No

No

0

 

  • Using the 50-50 Rule, what is earned value for this project?
  • Using the 0-100 Rule, what is earned value for this project?
  • Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.
  • Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?
  • What is the schedule performance index (SPI)?
  • Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?
  • What is the cost performance index (CPI)?
  • If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).
  • Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.