Using planbee scheduling software set up a project aon for


Using PlanBee scheduling software set up a project (AoN) for the project shown below, then display a PERT chart for the project. Simply capture the screen with something like Snagit and paste the JPG in here. I am suggesting PlanBee, because it is easy to learn. If you already have MS Project on your computer, you may use that instead.

A project consists of the following 5 elements. Assume that the CapEx (capital expenditure) takes place at the beginning of each element, that there are 40 working hours in a week, and that labor is charged at $100/hr. The precedents are given in the second column.

Element Dependencies CapEx Duration Total hrs

A Can start immediately $5,000 4 weeks 160

B Can start immediately $10,000 4 weeks 160

C B needs to be complete $8,000 2 weeks 80

D A and C need to be complete $12,000 1 week 40

E C needs to be complete $9,000 2 weeks 80

Give a cost estimate for the project referred to in Q-1 - without contingencies. Please include Capex (Materials) and Labour.