Using pert adam munson was able to determine that the


Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 16 a)What is the probability that the project will be completed in 8 months.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Using pert adam munson was able to determine that the
Reference No:- TGS02540726

Expected delivery within 24 Hours