Using order-of-magnitude estimating methods determine the


The estimated cost to construct a small polymerization plant is required before your firm's management will fund any preliminary design work. Data shows that a plant twice the size of the proposed plant cost $22M to construct. Using order-of-magnitude estimating methods, determine the estimated cost of the proposed plant.