Using fcfs and assuming the difference in arrival time is


Five jobs arrive nearly simultaneously for processing and their estimated CPU cycles are, respectively: Job A = 12, Job B = 2, Job C = 15, Job D = 7, and Job E = 3 ms.

a. Using FCFS, and assuming the difference in arrival time is negligible, in what order would they be processed? What is the total time required to process all five jobs? What is the average turnaround time for all five jobs?

b. Using SJN, and assuming the difference in arrival time is negligible, in what order would they be processed? What is the total time required to process all five jobs? What is the average turnaround time for all five jobs?