Using earned value measurements along with the other


Jennifer turned in her status report for the newly approved mailing activities. She feels that her pieces are on track with nothing for you to worry about. She reports the following information for the critical path tasks:

Task

Budgeted

Actual

Percent

Estimate

Planned

Planned

Actual

Projected

Planne

Actual

 

work!

work/

work

to

start

end

start

end date

Resource

Resource

 

cost

cost to

date

corrplete

complete

date

date

date

 

Uktration

Utilization

A

120 hours!

60 hours

30%

90 hours

4900

March 15

June 15

March 30

June 15

25%

30%

 

$1200

4600

 

 

 

 

 

 

 

 

8

120 hours!

50 hours

30%

60 hours

4600

April 1

May 15

April 8

May 30

50%

30%

 

$1200

4500

 

 

 

 

 

 

 

 

You review her status report and determine that Jennifer does not have a solid grasp of her status. Ben was unable to provide you with anything more than, "Things are moving along just fine."

• Using earned value measurements along with the other information and metrics available, determine the true status of Jennifer's portion of the project.

• Prepare an updated status report (1 page) for Jennifer and share the measurements and your rationale in your determination of the status for the project.

• Create a 2-3 slide presentation explaining the benefits of using EVM.

• Be sure to document some instructions (1-page document) for Jennifer and Ben for determining the project status for their next project update to you.

• Also, provide materials that would be used to train Jennifer and Ben on the benefits and application of earned value.

• The materials should include some guidelines for Jennifer and Ben to help them create and then interpret the metrics.

Solution Preview :

Prepared by a verified Expert
Other Subject: Using earned value measurements along with the other
Reference No:- TGS01124730

Now Priced at $40 (50% Discount)

Recommended (98%)

Rated (4.3/5)