Using AOA, diagram the network described below for Lillian Fok's construction project. Calculate its critical path. How long is the minimum duration of this network?

Activity

Nodes

Time (weeks)

Activity

Nodes

Time (weeks)

J

1-2

10

N

3-4

2

K

1-3

8

O

4-5

7

L

2-4

6

P

3-5

5

M

2-3

3

 

 

 