Using any approach you wish eg trial and error develop a


Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.

1. Using the resource loading chart, now compute the early/late start time, early/late finish time, and slack time for your project. Illustrate this new resource constrained network in a network diagram.

2. Complete the resource activity schedule.

3. For the new network, what is the new project duration?

4. Which activities are now critical?