Using 14 of the cost of capital calculate the npv for each


 Show calculations, no excel

Using 14% of the cost of capital calculate the NPV for each of the projects shown in the following table and indicate whether or not each is acceptable.

Project A Project B Project C Project D Project E

Initial cash outflow (CFo) (a)R 20 000 (b)R 600 000 (c) R150 000 (d) R 760 000 (e) R 100 000

1 (a)R 3 000 (b)R120 000 (c)R 18 888 (d)R 185 000 (e)R 0

2 (a)R 3 000 (b)R 145 000 (c)R 17 000 (d)R 185 000 (e)R 0

3 (a)R 3 000 (b)R 170 000 (c)R 16 000 (d)R 185 000 (e)R 0

4 (a)R 3 000 (b)R 190 000 (c)R 15 000 (d)R 185 000 (e)R 25 000

5 (a) R 3 000 (b)R 220 000 (c)R 15 000 (d)R 185 000 (e)R 36 000

6 (a) R 3 000 (b)240 000 (c)R 14 000 (d)R 185 000 (e)R 0

7 (a) R 3 000 (c)R 13 000 (d) R 185 000 (e) R 60 000

8 (a) R 3 000 (c) R 12 000 (d) R 185 000 (e) R 72 000

9 (a) R 3 000 (c) R 11 000 (e) R 84 000

10 (a) R 3 000 (c) R 10 000

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Using 14 of the cost of capital calculate the npv for each
Reference No:- TGS02408544

Expected delivery within 24 Hours