Use the following information to answer parts a through h


Question: Use the following information to answer parts a through h. Describe what the results of each calculation mean to you as a project manager. What do you propose to do?

PV = $25,000

EV = $30,000

AC = $29,000

BAC = $1,000,000

a. Schedule variance (SV)

b. Cost variance (CV)

c. Schedule performance index (SPI)

d. Cost performance index (CPI)

e. Estimate to complete (ETC-first method)

f. Estimate to complete (ETC-second method)

g. Estimate at completion (EAC)

h. To-complete performance index (TCPI)