Use the extended bottleneck model to solve problem with the


Question: Use the extended bottleneck model to solve Problem with the following number of pans in the system:

(a) N = 2 parts and

(b) N = 4 pans. Also determine the manufacturing lead time for the two cases of N in (a) and (b).

Problem: A flexible manufacturing cell consists of two machining workstations plus a load/unload station. The load/unload station is station I. Station 2 performs milling operations and consists of one server (one CNC milling machine). Station 3 has one server that performs drilling (one CNC drill press). The three stations are connected by a part handling system that has one work carrier. The mean transport time is 2.5 min. The FMC produces three parts. A, B, and C. The part mix fractions and process routings for the three parts arc presented in the table below. The operation frequency fijk = 1.0 for all operations. Determine:

(a) maximum production rate of the FMC,

(b) corresponding production rates of each product,

(c) utilization of each machine in the system, and

(d) number of busy servers at each station.

1754_Operation.png

Request for Solution File

Ask an Expert for Answer!!
Management Theories: Use the extended bottleneck model to solve problem with the
Reference No:- TGS02248654

Expected delivery within 24 Hours