Use the activity table below to determine the expected


Use the activity table below to determine the expected activity lengths and variances for each of the activities, using the beta distribution.

Activity

Time estimates: a, m, b (days)

1

3, 10, 20

2

3 ,5, 8

3

2, 6, 14

4

12, 20, 32

 

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: Use the activity table below to determine the expected
Reference No:- TGS0600689