Use MS Project to schedule the construction activities logically. Identify the critical path
| Activity Name |
Duration (Days) |
| Office Building Project |
|
| Submission/Approvals/Permits |
|
| Structural Steel Submittal |
20 |
| HVAC Submittals |
15 |
| MEP Coordination |
10 |
| Obtain Temp CO (Certificate of Occupancy) |
2 |
| Plumbing Inspections |
5 |
| Electrical Inspections |
7 |
| Electrical Utility Company Coordination/ Tie ins |
20 |
| Gas Utility Company Coordiation/ Tie ins |
9 |
| Water Utility Company Coordination/ Tie ins |
8 |
| Foundation |
|
| Site Clearing |
10 |
| Footing Excavation |
20 |
| Install Storm Sewer & Manholes/Inlets |
10 |
| Install Sanitary Sewer & Manholes |
10 |
| Install Underground Water Lines |
5 |
| Install Underground Electric Conduit |
5 |
| Form/Pour Concrete Footings |
20 |
| Form and Pour Column Piers |
15 |
| Form and Pour Bassment Slab |
10 |
| Backfill and Compact Footings |
5 |
| Structure |
|
| Fabricate Structural Steel |
45 |
| Erect Structural Frame |
35 |
| Floor Decking (1st & 2nd Floors) |
22 |
| Pour First Floor Slab |
12 |
| Erect Stairwell and Elevator Walls |
15 |
| Pour Second Floor Slab |
12 |
| Erect Roof Trusses |
7 |
| Plumbing and Electrical |
|
| HVAC First/Second Floors |
20 |
| Rough-In Eelctrical |
15 |
| Rough-In Plumbing/Piping |
11 |
| Install Wiring and Cable |
25 |
| Gas Piping Installs |
18 |
| Connect Equipment |
2 |
| Exterior Finishes |
|
| Brickface Exterior Walls |
36 |
| Roof |
|
| Insulation and Built-up Ply Roofing |
21 |
| Doors and Windows |
|
| Install Door and Window Frames |
6 |
| Install Exterior Doors and Windows |
9 |
| Install Interior Doors |
4 |
| Interior Finishes |
|
| Drywall in Offices |
36 |
| Flooring & Carpeting |
20 |
| Paint Building Interior |
22 |
| Plumbing and Lighting Fixtures |
|
| Install Lighting Fixtures |
10 |
| Install Plumbing Fixtures |
10 |
| Paving & Landcaping |
|
| Install & Compact Subgrade |
14 |
| Curbing, including Excavaton/Form/Pouring |
16 |
| Install Asphalt Base Course |
3 |
| Install Asphalt Surface Course |
2 |
| Linestriping and Signage |
5 |
| Landscaping |
5 |
| Punch List |
5 |