Use ms project to schedule the construction activities


Use MS Project to schedule the construction activities logically. Identify the critical path

Activity Name Duration (Days)
Office Building Project
Submission/Approvals/Permits
Structural Steel Submittal 20
HVAC Submittals 15
MEP Coordination 10
Obtain Temp CO (Certificate of Occupancy) 2
Plumbing Inspections 5
Electrical Inspections 7
Electrical Utility Company Coordination/ Tie ins 20
Gas Utility Company Coordiation/ Tie ins 9
Water Utility Company Coordination/ Tie ins 8
Foundation
Site Clearing 10
Footing Excavation 20
Install Storm Sewer & Manholes/Inlets 10
Install Sanitary Sewer & Manholes 10
Install Underground Water Lines 5
Install Underground Electric Conduit 5
Form/Pour Concrete Footings 20
Form and Pour Column Piers 15
Form and Pour Bassment Slab 10
Backfill and Compact Footings 5
Structure
Fabricate Structural Steel 45
Erect Structural Frame 35
Floor Decking (1st & 2nd Floors) 22
Pour First Floor Slab 12
Erect Stairwell and Elevator Walls 15
Pour Second Floor Slab 12
Erect Roof Trusses 7
Plumbing and Electrical
HVAC First/Second Floors 20
Rough-In Eelctrical 15
Rough-In Plumbing/Piping 11
Install Wiring and Cable 25
Gas Piping Installs 18
Connect Equipment 2
Exterior Finishes
Brickface Exterior Walls 36
Roof
Insulation and Built-up Ply Roofing 21
Doors and Windows
Install Door and Window Frames 6
Install Exterior Doors and Windows 9
Install Interior Doors 4
Interior Finishes
Drywall in Offices 36
Flooring & Carpeting 20
Paint Building Interior 22
Plumbing and Lighting Fixtures
Install Lighting Fixtures 10
Install Plumbing Fixtures 10
Paving & Landcaping
Install & Compact Subgrade 14
Curbing, including Excavaton/Form/Pouring 16
Install Asphalt Base Course 3
Install Asphalt Surface Course 2
Linestriping and Signage 5
Landscaping 5
Punch List 5

 

 

 

 