Use johnsons rule to determine the optimal sequence in


1) Jobs A, B, C, D and E must go through Processes I and II in that sequence (Process I first, then Process II). PLEASE SHOW WORK SO I KNOW HOW TO DO IT.

a) Use Johnson's rule to determine the optimal sequence in which to schedule the jobs to minimize the total required time.

b) If jobs were processed in the sequence: A-B-C-D-E, when will job 'B' be completed?

JOB

Required Processing Time on Process (Machine) I (in hours)

Required Processing Time on Process (Machine) II (in hours)

A

4

5

B

16

14

C

9

6

D

10

8

E

2

6

Request for Solution File

Ask an Expert for Answer!!
Mathematics: Use johnsons rule to determine the optimal sequence in
Reference No:- TGS02596291

Expected delivery within 24 Hours