Under what circumstances would you turn off effort driven


Answer the following questions (use MS Project help if necessary):
Define effort-driven?
Under what circumstances would you turn off effort driven scheduling?
Use a real-world example of when you would make a task as a Fixed Duration type task?
What is the formula for calculating duration?
What are the eight preset work contours (hint: In the Task Usage view right click on a resource name an open the assignment information box) and what are the procedures in applying them to a resource on a task?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Under what circumstances would you turn off effort driven
Reference No:- TGS0568915

Expected delivery within 24 Hours