Transmissions are delivered to the fabrication line four at


Transmissions are delivered to the fabrication line four at a time. It takes one hour for transmissions to be delivered. Approximately five vehicles are produced each hour, and management has decided that 40 percent of expected demand should be maintained as safety stock. How many kanban card sets are needed? (Round up your answer to the next whole number.)