Total variable costs of the project


Problem:

A firm is reviewing a project with labor cost of $8.80 per unit, raw materials cost of $25.05 a unit, and fixed costs of $12,000 a month. Sales are projected at 10,800 units over the 3-month life of the project.

Required:

Question 1: What are the total variable costs of the project?

Note: Please provide full description.