1. According to the Toyota Motor Company, which of the following is not one of the seven major waste categories?

a. Overproduction

b. Transportation

c. Motion

d. Single-piece flow

2. Total productive maintenance (TPM) seeks to do all of the following except ______.

a. Maximize equipment effectiveness.

b. Create worker ownership throughout the production process.

c. Foster continuous improvement efforts throughout the production process.

d. Enable multiple products in small batches to be run on the same equipment.

e. All of the above.