Problem: Wood Co. uses a predetermined overhead rate based on direct labor cost to apply manufacturing overhead to jobs. The predetermined overhead rates for the year are 200% for Department A and 50% for Department B. Job 123, started and completed during the year, was charged with the following costs:

                                               DEPT A     DEPT B
Direct materials                        $25,000     $5,000
direct labor                                   ?          $30,000
manufacturing overhead            $40,000         ?

The total manufacturing costs associated with Job 123 should be:

A) $135,000

B) $180,000

C) $195,000

D) $240,000