Total cost for the job on job cost sheet


The following data have been recorded for recently completed Job 674 on its job cost sheet. Direct materials cost was $2,039. A total of 32 direct labor-hours and 175 machine-hours were worked on the job. The direct labor wage rate is $14 per labor-hour. The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $15 per machine-hour.

The total cost for the job on its job cost sheet would be:

a) $2,967

b) $2,487

c) $2,068

d) $5,112