To reduce inventory costs your production dept would like


Chapters 13 & 14 (SCM 488)

1. Good intermediate planning requires coordinating demand forecasts with _______________to determine feasibility and strategic fit.

2. The outcome of the 3-18 month S&OP is an _____________updated weekly/monthly balancing production quantities, timing and resources needed to meet demand at minimum cost.

3. Aggregate plan capacity options seek what?__________________________________

4. Aggregate plan demand options seek what?____________________________________

5. Using a level scheduling strategy to meet an 8,500 unit expected demand over 250 production days ___________units are made each day. At this output level, if it takes 2.3 hrs. to make a unit and a person works 8 hrs per day  ___________workers are needed.  If a worker is paid $15/hr. __________is the total labor cost?

6. In your factory you decide to follow a level labor strategy.  23 pieces are made per day. 

What is the inventory at the end of Feb__________?  The total inventory carried over from one month to the next from Jan to April is ____________units.  With inventory carrying cost @ $2/unit per month, total carrying cost is_______________units.

7. To reduce inventory costs your production dept. would like to consider using part-time labor & subcontracting.  The output chosen is no longer 23; output chosen is to meet the month of lowest demand.  What is that output level (using the table in question 6)?

8. When producing this level of units/day over 80 production days, a total of __________units are made in-house.  If it takes 0.9 hrs to make each unit and workers work 7 hrs per day, how many full and part-time workers are needed______________? To meet the 1840 units demanded ___________will be outsourced. 

9. You are making a very simple product.  Your HR manager recommends hiring & laying off full-time & part time people to meet monthly demand.  It takes 2 hrs to make a unit and workers work 7 hrs per day.  How many workers are needed each month?


Expected demand per production day

Jan

12

Feb

25

Mar

25

April

18

10.  If it costs $200 to hire a worker and $400 to lay off a worker, how much is spent in total on hiring and laying off Jan through April?

11.  From the aggregate S&OP plan we know in broad terms what needs to be made.  The ______________breaks down (i.e. disaggregates) the plan into specific products to be made by when.   

12.  In this Bill of Material (BOM) we have _______ levels.  Circle the parent items in the BOM.

13.  In the above BOM, to make 100 items of A, how many of items B,C,D and E must be made?

14.  What is subtracted from a gross requirement plan to give you the net requirement plan?____________________

15.  In the below plan, your EOQ is 100 pieces.  What is the net requirement in week 5?


Week 1

Week 2

Week 3

Week 4

Week 5







Gross Requirements

60

40

10

20

40

Projected on hand

20

0

 

 

 

Net requirements

40

40

 

 

?

Planned order receipt

 

100

 

 

 

Planned order release

100

 

 

 

100

16.  As a manufacturing strategy, matching demand is best when set up costs are ________and holding costs __________.  EOQ is effective when demand is ____________.

Solution Preview :

Prepared by a verified Expert
Operation Management: To reduce inventory costs your production dept would like
Reference No:- TGS02540052

Now Priced at $20 (50% Discount)

Recommended (90%)

Rated (4.3/5)