Time savings to users are worth 35k per year and


Use PWs to calculate the benefit/cost ratio at i = 5% for a highway project. The first cost is $150K, and O&M costs are $5K per year. There is no salvage value after 20 years. Time savings to users are worth $35K per year, and neighborhood disruption is a disband fit of $10K per year. Is this project attractive?

Request for Solution File

Ask an Expert for Answer!!
Business Economics: Time savings to users are worth 35k per year and
Reference No:- TGS02604939

Expected delivery within 24 Hours