Three activities are candidates for crashing on a project


1. What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?

ACTIVITY

NORMAL TIME (DAYS)

CRASH TIME (DAYS)

NORMAL COST

CRASH COST

IMMEDIATE PREDECESSOR(S)

A

6

5

$ 900

$1,000

-

B

8

6

300

400

-

C

4

3

500

600

-

D

5

3

900

1,200

A

E

8

5

1,000

1,600

C

2. Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table:

a) What action would you take to reduce the critical path by 1 day?

b) Assuming no other paths become critical, what action would you take to reduce the critical path one additional day?

c) What is the total cost of the 2-day reduction?