They calculated a normal completion time of 53 days and a


Two project managers were given the following data for eight activities. They calculated a normal completion time of 53 days and a cost of £29,300 - or a crashed completion time of 40 days and a cost of £33,350. See how they got these results, and find how the cost of the project is related to its duration.

671_b3214b83-e2e1-4280-bf7f-76b6fefae018.png

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: They calculated a normal completion time of 53 days and a
Reference No:- TGS02222201

Expected delivery within 24 Hours