They are now breaking down the work packages into smaller


A project manager and his project team are planning the work to be done on a project. They have reviewed the customer requirements and have created an outline of the work breakdown structure and its corresponding WBS dictionary. They are now breaking down the work packages into smaller increments. What are they now trying to create?

1) A scope elaboration list.

2) A deliverable list.

3) An activity list.

4) A milestone list.