They are mutually exclusive and project risk has been


Project X is very risky and has an NPV of $3 million. Project Y is very safe and has an NPV of $2.5 million. They are mutually exclusive, and project risk has been properly considered in the NPV analysis. Which project should be chosen? Explain in no less than one paragraph.