There is a scheduled receipt of 100 cs in week 2 quantities


Given the following product tree, determine the low-level codes and the gross and net quantities for each part. There is a requirement for 100 As in week 4 and 50 Bs in week 5. There is a scheduled receipt of 100 Cs in week 2. Quantities required of each are also shown.